Project Summary
Tenant representatives for a 25,000 SF build-to-suit office building near
St. Louis. The program included 136 workstations, 2,000 SF sever room
with a 60 KVA UPS. The building AC system was upgraded from 30 tons to
90 tons to accommodate the high density workstations and lab environment,
coordinated the installation of a specialized physical security system.
|